Construction Updates

Follow the progress of the store as it comes to life.

To see the start of the project, go to the last page.

Tamie Kikuchi Tamie Kikuchi

26 January 2026

Rainwater management system

Civil engineers are on site installing a system to manage rainwater. This work is part of the site’s development permit requirements.

Read More
Tamie Kikuchi Tamie Kikuchi

9 January 2026

Drywall installation

The carpenters have begun fitting drywall to the interior walls. A cedar ceiling will be installed soon.

Read More
Tamie Kikuchi Tamie Kikuchi

20–23 December 2025

Electrical work underway

Two electricians have been installing cabling for all key systems, from lighting and outlets to speakers and the security setup. I’ve been impressed by how quickly and meticulously they’ve been working.

Read More
Tamie Kikuchi Tamie Kikuchi

17 December 2025

Site clearing

A local landscaping crew cleared the south side of the land, removing branches, tree stumps, and the grass that my husband and I cut back in October. It was a particularly cold morning, with frost still on the ground as the crew began work. Over the coming months, a civil engineering company will carry out additional ground and site work.

Read More
Tamie Kikuchi Tamie Kikuchi

16 December 2025

Interior scaffolding installed

Scaffolding was installed inside the shop a few days ago, allowing the contractors to work safely at higher levels. The carpenters are continuing their work in preparation for the insulation work planned for later this month.

Read More
Tamie Kikuchi Tamie Kikuchi

12 December 2025

Site protection added

The scaffolding is now wrapped in green sheeting, helping protect the site as work continues.

Read More
Tamie Kikuchi Tamie Kikuchi

11 December 2025

Front entrance and exterior walls

Work began on installing the automatic doors at the shop entrance. With plenty of glass at the front, the design creates an open and welcoming feel. Protective sheeting was also added over the exterior structural walls.

Read More
Tamie Kikuchi Tamie Kikuchi

10 December 2025

Structural walls and interior carpentry

Installation of the exterior structural walls is now complete, marking another important step in the build. 

Inside the shop, carpenters continued their work, revealing exposed beams and a high ceiling that give the space an open feel. Although the building is one storey tall, the highest part of the ceiling rises to the height of two storeys. The framing inside the walls is made from Japanese cypress (hinoki), and the lovely scent of the wood fills the space.

Read More